Friday, March 6, 2015

Practical Application of Dude's Law: The Value Estimation Game

Last summer, Todd Kromann and I presented on Dude's Law at Agile2014, and I figured it was high time that I wrote a blog post to walk through what we covered.

Dude's Law

If you're not already familiar with the Agile Dude, David Hussman, we highly recommend becoming familiar. David is most well-known for his coining of Dude's Law, which states that "Value = Why / How". The intent behind Dude's Law was to help teams avoid what David refers to as the "Recipe Trap" - doing things because that's what the "recipe" (read prescribed methodology or management mandate) says you're supposed do.

Dude's Law: Value = Why / How

Using Dude's Law as a coach is extremely powerful.It's a simple way for people to question everything they do. It emphasizes the need to know why we do the things we do. It resonates with people at an almost instinctual level.

WSJF

The more Todd and I used Dude's Law in our coaching, the more applications we found for it. Eventually, we noticed the similarities between Dude's Law and Don Reinertsen's concept of "Weighted Shortest Job First", or WSJF.

WSJF is a powerful prioritization tool. There are basically three underlying principles to WSJF. First, if all the work you have to do is the same size, you do the job with the highest cost of delay first. In other words, we want to do the work that is the most urgent or will cost us the most to not do. After all, if all the work items are going to cost us the same amount then we want to get the most out of the time spent.

Second, if all the work you have to do has the same cost of delay, do the shortest job first. In other words, if all work is equally expensive to not do then we want to start getting benefit as quickly as possible.

Third, if both the size and cost of delay are variable, do the weighted shortest job first. You do this by dividing the cost of delay by the size; the higher the result, the sooner the work in question should be executed. Since our highest cost is typically the manpower necessary to do the work, size is defined by duration. Duration is also useful as the denominator because it emphasizes the need to get things delivered quickly, so we have a bias towards smaller slices of value.

WSJF = Cost of Delay / Duration

Where's the work?

Before we go any further, we need work items. If you're applying this within a team, simply use the work that's already on your backlog (or slated to go on your backlog). Application of WSJF (or Dude's Law) tends to work best at the Epic or Feature level, but can be applied to User Stories as well.

If you don't have real-world work, you can do what we do - have the team(s) come up with their own work. We usually run this with multiple "table teams" - teams formed around tables in the room. We like to get one set of Features for the whole room so we can see the differences in prioritization by each group (it makes for some interesting conversation at the end of the workshop). To do this, we tell the room that we have a great idea for a game, but all we have is a title. Based on our market research, we know this title is a winner. We want to build "Angry Flappy Candy Bird Crush Saga". We then solicit five Features from the room that we think are essential to become profitable as quickly as possible. Voila! We now have the beginnings of a backlog.

Estimation Game

The key to applying WSJF (or Dude's Law) in the context of prioritization is the quantification of those values. We need numbers so we can do an actual numeric division to get a numeric value for WSJF (or Value). How do we do this? We highly recommend relative estimation! The most common way to use relative estimation is to use Fibonacci numbers to size items relative to each other. If you've never done this before, this can be daunting - especially for your first work item, when you do not yet have anything to compare the item's size against.

The technique that we use in this workshop is called the "Team Estimation Game". This technique works well to quickly get an initial backlog estimated. Since most people are used to estimating size anyway, we have teams estimate the size (what we refer to as "Cost of Implementation") first using the Team Estimation game. Once they're done, we have them write the number on the bottom of each story card, in the center.

The Team Estimation Game summarized

Cost of Delay

Now that we've estimated the cost of implementation, we need to estimate the cost of delay. We do this with the exact same approach we used for cost of implementation. When trying to figure out cost of delay, think of it in terms of, "How expensive is this to not do?"

When considering cost of delay, there are several factors we need to consider: inherent value to the business; urgency due to any number of reasons (legal deadlines, market demands, partner collaboration, etc.); the value of other work that's dependent on this work item being done first; risks that this item may reduce; and so on.

When we're talking about benefit, we usually use the priority scale where 1 is most important, then 2, then 3, etc. That is not what we're doing here. In this case, a 1 is something with a very low cost of delay - it's not very urgent, valuable, etc. The higher the number, the more expensive it is to not do.

Once each card has a number value, write it in the bottom left corner of the card.

Run the Math

Now that we have the two variables on the right side of the equation, we need to "run the math" to see what our WSJF (or Dude's Law) number - what we call the Value Index - comes out to be. For each card, divide the Cost of Delay (bottom-left number) by the Cost of Implementation (bottom-center number) and put the result, the Value Index, in the bottom-right corner. Order the cards from highest Value Index to lowest Value Index. This is now the priority that the math recommends you complete the work in.

As long as your estimation was honest, doing the work in this order will give you the greatest return on your investment over time. We can maximize how much we capitalize on our work as soon as possible. The below graphs help illustrate this.

Add value sooner with WSJF/Dude's Law

Remember Dude's Law

What we often find is that the first time people use this approach their prioritization is a little wonky. That's okay - the purpose of this exercise isn't to mandate what order you do things in. This approach is a conversation framework to help teams make sure they're working on things in the right order, factoring cost of implementation into the prioritization process instead of looking only at short-term benefit. Teams also find that this tool becomes more beneficial as they gain experience with it - they learn what they need to discuss in order to come to proper estimates that lead to better prioritization.

Remember the original intent behind Dude's Law: to avoid the Recipe Trap. This approach is not intended to be a recipe for the team to follow blindly. This is a tool, one that the team should understand the benefits of before they decide to adopt it. Understand the Why before jumping into the How.

You may also decide to elaborate on the formula. You may take the SAFe approach and discuss different factors to Cost of Delay instead of having a single number. You may decide to incorporate IBM's approach of Value Dials and ITBV. You may end up with a multi-sheet Excel workbook with dozens of numeric inputs that feed into a complicated formula. In the end, it all boils down to Why/How. Be careful how much extra time you put into prioritization and make sure the improvements to your prioritization justify that extra time.

Friday, February 27, 2015

Revisiting Normalized Story Points

It has been just over 18 months since I published my most popular blog post to-date: "Normalized Story Points". As of this writing, it has received over 5,400 page views, thanks primarily to the reference it has from Dean Leffingwell's blog post from ScaledAgileFramework.com entitled "More on Normalizing Story Point Estimating".

As an Agile Coach who takes continuous improvement seriously, I have learned much and grown much over the last year and a half. Here are a few of the things I've learned regarding Normalized Story Points.

Know Why You Want Them

I've become a HUGE fan of David Hussman's "Dude's Law". Before you do anything, you need to know WHY you're doing it, not just HOW to do it.

The purpose of Normalized Story Pointing is to enable high-level estimation of work for a SAFe Release Train comprised of closely aligned teams, any one of which may pull a Feature off the Program Backlog for implementation. Normalized Story Points should not be used for:
  1. Comparing teams against each other
  2. Forcing teams to use the same story point size (so that "1 Story Point" means exactly the same thing to everyone forever and ever amen)
  3. Defining "Story Point" to mean "Ideal Man-Day"
  4. Any punitive purpose
If you don't know why you're using Normalized Story Points, don't use them. If your intended use of Normalized Story Points violates the mindset established by the Agile Manifesto, don't use them (although, if this is the case then you probably won't realize it unless someone points it out to you).

Beware the Ideal Man-Day

The 4-step process for getting started with Normalized Story Points involves using time as a reference. This works well because you're using a very small story, one with very little complexity, which means the primary factor for determining "bigness" is lapsed time. That being said, I've found that teams that start with this approach have a very, very difficult time recovering from the mindset of "1 point == 1 ideal man-day". This is bad for reasons.

This also leads to teams always using days of availability to forecast velocity rather than taking a rolling average velocity or "yesterday's weather" as an indicator of what they're likely to deliver. Data trumps theory; the approach to get started is based on theory, while average velocity is data.

Individuals and Interactions over Processes and Tools

Processes and tools exist to enhance and enable interactions between individuals, not replace them. As I've explained in a previous post, the process of Agile estimation is beneficial primarily because of the conversation that it fosters. It's a well-formed game that drives a shared mental model of the work for the entire team.

I've found that teams that use Normalized Story Points may skimp on the conversation, especially if one team ends up with work that another team has already estimated (after all, we all share the same definition of story point, right?). This was never the intent behind Normalized Story Points, but that doesn't mean it doesn't happen.

Beware the Recipe Trap

David Hussman explained that he uses "Dude's Law" to help teams avoid what he calls the "Recipe Trap" - doing something because that's what the recipe says to do, without understanding what the intended benefits are. When it comes to Normalized Story Points, the recipe trap is very real and very dangerous. If you use it, be very careful about how you explain and implement it with your teams. If your teams can't all pull from a common backlog; if you're going to use them to run punitive metrics; if you want to streamline your process by reducing meaningful conversation; or if you're looking to use it because that's what SAFe says to do, I plead with you to reconsider.

TL;DR: Normalized Story Points can be a useful tool for your organization, but it's not a one-size-fits-all solution.